Ludlow Commons is an 8-story, 71-unit affordable senior living development that supports independent senior living. During construction, the project was delayed at least 3 months right from the beginning as a huge dewatering undertaking was necessary to begin pouring the foundation due to a higher than anticipated water table. The General Contractor went above and beyond to complete the project very close to the original contract date.
Location
Yonkers, New York
Client
Westhab
Architect
Magnusson Architecture & Planning
General Contractor
Lasberg Construction Associates, Inc.
Services
Owner’s Representative
Original Budget
$17.9 Million
Construction Cost
$XX
Original Quoted Duration
18 Months
Actual Duration
20 Months
Olive Branch Consulting has been an invaluable partner to Westhab. We’ve come to expect consistent, professional and thorough input and direction from OBC, which has helped us move our real estate development projects forward, saving us both time and money.
Richard Nightingale // President & CEO, Westhab, Inc.
This team was strategically selected for the Ludlow Commons project.